Skip to main content

Drawing No. EH–PG–008 // Power Generation & Grid

Worked Example: Datteln 4 Coal Power Station Water Usage

Reviewed August 2026

A real-world water-balance example for Datteln 4, the 1,052 MWe net hard-coal power station in North Rhine-Westphalia, Germany. Unlike the BWRX-300 worked example, this case is anchored to a published water permit: up to 2,300 m³/h and 15 million m³/year may be withdrawn from the Dortmund-Ems Canal for plant operating water.

Important: published permit limits are not the same as normal operating flow. The split between cooling-tower makeup, FGD/process water, demineralized-water production and other users below is an EngineerHub engineering reconstruction designed to fit the published permit envelope. Replace assumptions with plant operating records where available.
Published plant value1,052 MWe

Net electrical output reported by Uniper.

Water permit2,300 m³/h

Maximum Dortmund-Ems Canal withdrawal.

Annual permit15.0 Mm³/y

Maximum permitted annual withdrawal.

Published efficiency>45%

Modern hard-coal unit; model starts at 45% net efficiency.

What the permit tells us directly

The 19 January 2017 water permit authorizes up to 639 L/s = 2,300 m³/h, 55,000 m³/day and 15,000,000 m³/year from the Dortmund-Ems Canal. It states that operating water is used mainly to replace cooling-tower evaporation, as cooling-tower and flue-gas-desulfurization process water, and to produce fully demineralized water for the steam/water cycles. The environmental assessment also notes that using collected precipitation can reduce operating-water withdrawal by up to 25%. Official withdrawal permit ↗

Display units

Cooling-tower assumptions

editable reconstruction

Datteln 4 uses a large natural-draft wet cooling tower. The exact operating range, cycles and latent fraction are not quoted in the public permit and remain assumptions here.

Auxiliary-water assumptions

FGD + high-purity + service

The permit names FGD and fully demineralized water as plant water users, but does not expose their normal flow split. These starting values are transparent estimates.

Rainwater credit & annualization

permit sensitivity

The environmental assessment says precipitation use can reduce operating-water withdrawal by up to 25%. The 70% annual utilization is illustrative and is not a published Datteln 4 capacity factor.

Open full water-balance toolCompare BWRX-300

Permit-constrained result

modeled full-load condition
Gross plant water demand
before rainwater credit
Canal withdrawal
Net consumption
evaporation + process losses
Industrial liquid discharge
before downstream treatment
Permit headroom
vs 2,300 m³/h permit
Annual canal withdrawal
Mass balance: calculating…

Cooling & process breakdown

model reconstruction
Estimated thermal input
Non-electric heat
Estimated heat to cooling tower
Cooling-water circulation
Tower evaporation
Drift
Blowdown
Gross tower makeup
FGD / process raw water
Demineralization raw feed
Other service/process water

Detailed plant balance

estimated flow streams
Streamm³/hm³/day

Published permit vs engineering reconstruction

keep facts separate from assumptions

ParameterValueStatusBasis
Net electrical output1,052 MWePublishedUniper's 2025 sale announcement for Datteln 4.
Gross electrical output1,100 MWePublishedPublic plant descriptions and project material.
Net efficiency>45%PublishedPublic plant descriptions. Model uses 45.0% as an editable screening value.
Canal withdrawal permit2,300 m³/h; 55,000 m³/day; 15.0 Mm³/yearPublished2017 Dortmund-Ems Canal water-withdrawal permit.
Fish-protection returnup to 35 m³/h to Dortmund-Ems CanalPublishedSeparate permit item for Multidisc fish-return water; excluded from the process balance below.
Rainwater reduction potentialup to 25%PublishedEnvironmental assessment says supplemental precipitation use can reduce operating-water withdrawal by up to 25%.
Cooling range / cycles / evaporation spliteditableEstimateNot exposed as normal operating values in the public withdrawal permit.
FGD, demin and service-water spliteditableEstimatePermit names these uses but does not publish the normal flow allocation.

Where the wastewater goes

separate process water from stormwater

Industrial plant wastewater → treatment plant → Lippe

The 2017 environmental decision refers to the approved indirect discharge of Datteln 4 process wastewater through the Dattelner Mühlenbach wastewater treatment plant and onward to the Lippe. The modeled liquid discharge on this page represents the plant-side flow before that downstream treatment.

Fish-return water → Dortmund-Ems Canal

The withdrawal permit separately allows up to 35 m³/h to be returned to the canal from operation of the Multidisc fish-protection system. This is not treated as FGD or cooling-tower wastewater in the worked balance.

Treated precipitation → Deinebach

A separate water permit allows treated precipitation from the Datteln 4 site to be discharged to the Deinebach, up to 180 m³/h. This is a stormwater-management stream and is excluded from normal operating process-water demand here.

Storm-event overflow → Dortmund-Ems Canal

A separate permit allows large precipitation-water discharge to the Dortmund-Ems Canal during heavy rainfall only. It explicitly does not authorize continuous discharge, so it is not part of the normal-operation water balance.

Calculation method

how the reconstruction is built

1. Heat balance

The model converts net electrical output and editable net efficiency into thermal input:

in = Pnet / ηnet

At 45% net efficiency, 1,052 MWe implies about 2,338 MW thermal input and roughly 1,286 MW not exported as electricity.

2. Cooling circulation

A selected share of non-electric heat is assigned to the cooling tower. Circulation follows:

V̇ = Q̇ / (ρ cp ΔT)

The default 12 °C range gives an order-of-magnitude circulating flow of about 85,000 m³/h.

3. Evaporation and blowdown

Evaporation is tied to latent heat and blowdown is derived from cycles of concentration:

E = flatentQ̇/(ρhfg)
B = E/(C−1) − D

4. Permit check

Cooling makeup is added to estimated FGD/process, demineralization and service water. Any rainwater credit reduces the canal draw, not the underlying plant water demand.

Canal draw = Gross demand × (1 − rainwater credit)

5. Annual permit

The 15 million m³/year limit corresponds to only about 6,522 hours/year at the maximum 2,300 m³/h withdrawal—about 74.4% of a full calendar year. Actual annual withdrawal therefore depends strongly on dispatch and rainwater substitution.

6. Interpretation

This is a constrained engineering reconstruction, not a reproduction of Datteln 4 operating logs. Its value is showing whether a plausible heat- and solids-balance can fit within a real permitted water envelope.

References

official sources first

Bezirksregierung Münster — 2017 water-withdrawal permit for Datteln 4. Authorizes up to 2,300 m³/h, 55,000 m³/day and 15,000,000 m³/year from the Dortmund-Ems Canal. It identifies cooling-tower evaporation/process water, FGD and demineralized-water production as operating-water uses and separately allows up to 35 m³/h fish-return water to the canal. Permit PDF ↗
Bezirksregierung Münster — Datteln 4 approval documents. Official index for the plant operating approval and water permits. Approval page ↗
Bezirksregierung Münster — 2017 plant approval / environmental assessment. Notes that operating-water withdrawal may be reduced by up to 25% through precipitation-water use and documents the indirect discharge route of plant wastewater via the Dattelner Mühlenbach treatment plant to the Lippe. Approval PDF ↗
Uniper — sale of Datteln 4, September/December 2025. Reports 1,052 MW net electrical output, commissioning in 2020 and the plant's status as a modern flexible hard-coal station. Uniper source ↗
Onyx Power — Datteln 4. Current plant page describing the >1,000 MW station, combined heat and power operation and district-heating role. Current plant page ↗
Wilbert TowerCranes — Datteln 4 cooling tower project. Documents the large natural-draft cooling tower and the plant's >45% net-efficiency design basis. Cooling-tower project ↗

Reference status checked 21 August 2026. Published permit values are kept distinct from EngineerHub flow assumptions throughout the page.

Compare the water-balance examples

same framework, different evidence