How to use this learning simulator
Start with the corridor map and select a transmission technology. Change power, voltage and distance to see current and losses. Then use the transformer and substation modules to follow electricity through voltage conversion and switching equipment.
01 // Interactive transmission corridor & loss calculator
The stylised map represents a generating region, a selected transmission corridor and a distant load centre. It is not a real geographic network, and the background terrain does not imply that every selectable technology is suitable for that route. Select the corridor or a technology card to update the route and calculation assumptions.
Corridor inputs
Technology preset
AC assumptions
Converter assumptions
Corridor result
What actually limits a transmission corridor?
The calculator compares power with an entered MW rating, but a real operating limit is the lowest acceptable limit from several different studies—not simply the conductor's nominal current capacity.
Start with 220 kV, note the current and loss, then load the 400 kV case. Next compare the long HVAC cable with HVDC on the same route.
02 // Transmission-line and cable explorer
No single technology is best in every location. Route length, power, land access, water crossings, planning constraints, repair strategy, system strength and converter or compensation requirements all matter.
Overhead conductor
Air provides insulation. Conductors are exposed to weather and require wide electrical clearances and rights-of-way.
Extruded underground cable
Compact and visually unobtrusive, but thermal environment, joints, repair access and AC capacitance are important.
Submarine cable
Armouring and marine installation protect the cable. Route survey, burial, crossing design and repair logistics dominate.
Gas-insulated line
Enclosed high-voltage conductor systems can provide compact connections in tunnels or constrained substation areas.
| Technology | Typical strength | Main limitation | Intermediate taps | Power-flow control | Visual footprint |
|---|---|---|---|---|---|
| HVAC overhead | Meshed network integration | Right-of-way and visual impact | Relatively straightforward | Follows AC network physics | High |
| HVAC cable | Dense or sensitive routes | Charging current and thermal repair | Possible but costly | Follows AC network physics | Low above ground |
| HVDC cable | Long submarine/underground transfer | Converter cost and complexity | Complex multi-terminal design | Directly controllable | Low route footprint |
| HVDC overhead | Very long bulk transfer | Converter terminals and DC protection | Less common | Directly controllable | High |
03 // Transformer performance lab
Transformers make AC transmission practical by raising generator voltage and connecting different grid levels. The model includes no-load loss, load-dependent loss, output loading, a direct output-voltage adjustment and approximate current on both sides.
Transformer inputs
At partial load, no-load core loss remains approximately constant while winding loss falls roughly with current squared.
04 // Substation busbar and switching simulator
A substation is not merely a transformer site. It contains busbars, breakers, disconnectors, instrument transformers, surge arresters, protection, control, auxiliary systems and connections to incoming and outgoing circuits.
05 // HVAC versus HVDC
Most transmission networks are AC because transformers, protection and intermediate network connections are mature and widely deployed. HVDC is added where controlled point-to-point transfer or long cable distance offers a system benefit.
Alternating current
Voltage and current reverse direction periodically. Multiple AC generators remain synchronized within a synchronous area.
Direct current
Polarity remains fixed. Power-electronic converters control transfer and connect the DC link to one or more AC systems.
| Question | HVAC | HVDC |
|---|---|---|
| How is voltage changed? | Conventional power transformers | Power-electronic converter stations plus AC transformers |
| How does power flow? | Determined by network impedance and angle differences | Converter controls schedule the link transfer within limits |
| Long cable behaviour | Charging current and reactive compensation become important | No periodic AC charging current in normal DC operation |
| Connect asynchronous grids? | Not directly | Yes, through the DC link |
| Intermediate network connections | Routine in meshed grids | Possible but multi-terminal systems are more complex |
| Terminal cost and loss | Generally lower terminal complexity | Significant converter investment and converter losses |
| Fault interruption | Mature AC breakers and protection | DC fault interruption and multi-terminal protection are more demanding |
06 // Real transmission project examples
These short examples show why different transmission technologies are selected. The simulator calculations are generic and do not reproduce these projects.
Gotland HVDC — technology milestone
The original Gotland link entered service in 1954 and is widely recognised as the first commercial HVDC transmission system.
NorNed — long submarine interconnector
NorNed connects Norway and the Netherlands through a long HVDC submarine cable and supports controllable cross-border exchange.
North Sea Link — large interconnector
The Great Britain–Norway link illustrates modern high-capacity, long-distance submarine interconnection.
07 // Transmission engineering background
Open the topics below for the main physical and operational ideas represented by the simulator.
Lines, voltage and power
For a balanced three-phase AC line, active power is approximately:
P = √3 · VLL · I · PFFor a given power and power factor, a higher voltage produces a lower current. Resistive heating is approximately:
Ploss = 3 I² RBecause current is squared, lowering current has a strong effect on loss.
MW is active power transferred into useful work or heat. MVAr is reactive power associated with electric and magnetic fields and voltage support. MVA is apparent power—the combined magnitude that drives equipment current and rating.
S² = P² + Q² and PF = P / SFor the same MW, lower power factor means higher MVA and therefore higher current.
In a meshed AC network, active power divides among parallel paths according to network impedance and voltage-angle differences. Opening one line changes the impedance network, so power redistributes automatically to remaining paths.
P12 ≈ (V₁V₂ / X) sin(δ₁ − δ₂)This simplified lossless relation explains why lower reactance and larger angle difference increase active-power transfer. It is not a load-flow solution and should not be used near stability limits.
Cable conductors are close to their grounded metallic screens, producing much higher capacitance than an overhead line. AC voltage continually charges and discharges this capacitance, creating charging current and reactive power even when useful load power is low.
Qc ≈ 3 · 2πf · C · Vphase²Compensation, thermal current and voltage control therefore become important as AC cable length increases. The calculator reports charging MVAr and its equivalent current separately; it does not solve the distributed voltage and reactive-power profile or add charging current to the displayed I²R loss.
- Conductor temperature and sag for overhead lines.
- Cable conductor and insulation temperature.
- Voltage stability, transient stability and angle limits.
- Reactive-power capability and voltage control.
- Protection, short-circuit level and equipment ratings.
- Post-contingency security rather than normal-state loading alone.
Shunt reactors absorb reactive power from long AC cables and lightly loaded lines. Capacitor banks, generators, synchronous condensers, SVCs and STATCOMs can supply or absorb reactive power to regulate voltage. Series compensation changes effective line reactance and can increase transfer capability, but protection and stability interactions require detailed study.
The corridor calculator does not size compensation equipment or calculate the distributed receiving-end voltage profile.
Transformers and substations
Alternating current in the primary winding establishes alternating magnetic flux in the core. That changing flux induces voltage in the secondary winding.
V₁ / V₂ ≈ N₁ / N₂Power transformers also have leakage impedance, core loss, winding loss, thermal limits, insulation requirements and tap-changing arrangements.
A busbar is a high-current electrical node connecting line bays, transformer bays, reactors, capacitor banks and other equipment. Busbar arrangement determines how flexibly circuits can be maintained or isolated after a fault.
A circuit breaker is designed to interrupt normal and fault current within its rating. A disconnector creates a visible or assured isolation gap but is generally not used to interrupt significant load or fault current. Operating sequences and interlocks are safety-critical.
AIS: air-insulated switchgear uses open-air clearances, is visually accessible and generally occupies more land.
GIS: gas-insulated switchgear places conductors and switching equipment in compact grounded enclosures. It reduces footprint but increases specialised equipment, interfaces and repair considerations.
Protection systems identify faults and trip the correct breakers. Main and backup schemes, duplicated measurement and trip paths, breaker-failure protection, communication and DC auxiliary supplies are used so one failure does not defeat fault clearance.
Sources and further reading
The simulator uses simplified equations and qualitative equipment descriptions. The following official and primary sources provide context for real transmission planning, transformer resilience, cables, HVDC operation and substation protection.
Related EngineerHub electrical tools
Continue from transmission principles into system operation, voltage drop, transformer ratios and circuit calculations.