Skip to content

Drawing No. EH–EE–027 // Electrical Engineering

Power Transmission Simulator

Reviewed August 2026

Explore how bulk electricity moves between regions. Compare overhead lines, underground and submarine cables, HVAC and HVDC, transformer performance, voltage levels, substation layouts, switching arrangements and corridor losses.

Educational model: The calculations deliberately simplify three-phase steady-state transmission. They do not replace detailed load-flow, reactive-power, electromagnetic-transient, protection, insulation-coordination, thermal-rating or civil-design studies.

How to use this learning simulator

Start with the corridor map and select a transmission technology. Change power, voltage and distance to see current and losses. Then use the transformer and substation modules to follow electricity through voltage conversion and switching equipment.

01 // RouteChoose land, underground or submarine transmission.
02 // TransferCompare current, resistive loss and AC cable charging.
03 // TransformChange voltage and examine transformer loading and efficiency.
04 // SwitchCompare substation busbars under faults and maintenance.

01 // Interactive transmission corridor & loss calculator

The stylised map represents a generating region, a selected transmission corridor and a distant load centre. It is not a real geographic network, and the background terrain does not imply that every selectable technology is suitable for that route. Select the corridor or a technology card to update the route and calculation assumptions.

Educational power transmission corridor A generation area connects through substations, overhead lines, a sea crossing and a load centre. GENERATION REGION LOAD REGION SELECTED CORRIDOR GENERATION21 kV AC STEP-UP S/S21 / 400 kV CONVERTER AAC / DC CONVERTER BDC / AC GRID S/S400 / 132 kV METRO LOAD132 kV 21 kV AC 400 kV AC ±320 kV DC 400 kV AC 132 kV AC
Voltage pathVoltage is raised for bulk transfer and reduced again near customers. The selected corridor voltage updates with the technology preset.
Generator21 kV ACGeneration voltage
Step-up transformer400 kV ACLower current for transfer
VSC-HVDC corridor±320 kV DCSelected bulk corridor
Receiving grid400 / 132 kV ACGrid transformation
Regional load132 kV ACSubtransmission level

Corridor inputs

Technology preset

For HVAC, this is active power entering the line. For HVDC, it is AC-bus power available before sending-converter and station-auxiliary losses.
Use effective operating resistance for one AC phase conductor or one DC pole. For bundled conductors, enter the equivalent phase or pole value.
Parallel paths are assumed identical and equally loaded.
An entered active-power screening limit—not a calculated thermal, voltage-stability or transient-stability rating.
Used only for annual energy-loss estimation. Resistive loss scales approximately with current squared.
Annual assumption: The link is treated as energized for 8,760 hours. For HVDC, entered station auxiliary demand is treated as continuous; for HVAC, terminal and compensation-equipment losses are not included.

Converter assumptions

The DC model assumes a balanced symmetrical bipole with equal pole resistance. Monopole, metallic-return and earth-return operation are not modelled.
Resistance, capacitance, thermal rating and converter losses vary with conductor, cable design, temperature, installation and manufacturer. Presets are illustrative rather than catalogue data.

Corridor result

Transfer within selected ratingThe illustrative link remains below its entered power rating.
Transfer current
Per pole or phase
Delivered power
After modelled losses
Conductor loss
Resistive I²R estimate
Terminal / converter loss
AC terminals not modelled
Modelled efficiency
Delivered / sent power
Capacity loading
Power / entered rating
AC cable charging
Reactive power and current
Annual energy loss
Using entered annual average transfer
Teaching point: High voltage reduces current for the same transferred power, which strongly reduces resistive loss.

What actually limits a transmission corridor?

The calculator compares power with an entered MW rating, but a real operating limit is the lowest acceptable limit from several different studies—not simply the conductor's nominal current capacity.

Thermal limitConductor temperature, overhead-line sag, cable insulation temperature and equipment current ratings.
Voltage & reactive powerReceiving-end voltage, reactive-power balance, cable charging and available compensation or voltage support.
Stability limitRotor-angle, oscillatory and voltage-stability margins can limit transfer before a conductor reaches its thermal rating.
Contingency limitThe network must retain acceptable performance after credible outages, protection actions and equipment unavailability.
Static versus dynamic line rating: overhead-line thermal capacity changes with wind, ambient temperature and solar heating. Dynamic line rating can estimate weather-dependent capacity, but it does not remove voltage, stability or contingency limits.
Guided experimentsLoad two related cases and compare current, conductor loss, charging current and terminal loss.

Start with 220 kV, note the current and loss, then load the 400 kV case. Next compare the long HVAC cable with HVDC on the same route.

02 // Transmission-line and cable explorer

No single technology is best in every location. Route length, power, land access, water crossings, planning constraints, repair strategy, system strength and converter or compensation requirements all matter.

Overhead conductor

Air provides insulation. Conductors are exposed to weather and require wide electrical clearances and rights-of-way.

Extruded underground cable

SHEATHINSULATIONCONDUCTOR

Compact and visually unobtrusive, but thermal environment, joints, repair access and AC capacitance are important.

Submarine cable

Armouring and marine installation protect the cable. Route survey, burial, crossing design and repair logistics dominate.

Gas-insulated line

Enclosed high-voltage conductor systems can provide compact connections in tunnels or constrained substation areas.

TechnologyTypical strengthMain limitationIntermediate tapsPower-flow controlVisual footprint
HVAC overheadMeshed network integrationRight-of-way and visual impactRelatively straightforwardFollows AC network physicsHigh
HVAC cableDense or sensitive routesCharging current and thermal repairPossible but costlyFollows AC network physicsLow above ground
HVDC cableLong submarine/underground transferConverter cost and complexityComplex multi-terminal designDirectly controllableLow route footprint
HVDC overheadVery long bulk transferConverter terminals and DC protectionLess commonDirectly controllableHigh

03 // Transformer performance lab

Transformers make AC transmission practical by raising generator voltage and connecting different grid levels. The model includes no-load loss, load-dependent loss, output loading, a direct output-voltage adjustment and approximate current on both sides.

Transformer inputs

The voltage adjustment is an educational direct output-voltage change, not a detailed on-load tap-changer model. No-load loss is treated as constant at the entered energized condition, while rated-current load loss scales with loading squared. Magnetizing current, leakage impedance, voltage regulation, harmonics, temperature correction, thermal ageing and parallel operation are not calculated.
INPUT SIDE OUTPUT SIDE 400 kV 135.3 kV MAGNETIC CORE RATIO 3.03 : 1
Input-side current
Output-side current
Active output
Active input
Total loss
Efficiency
Adjusted output voltage
Voltage conversion

At partial load, no-load core loss remains approximately constant while winding loss falls roughly with current squared.

04 // Substation busbar and switching simulator

A substation is not merely a transformer site. It contains busbars, breakers, disconnectors, instrument transformers, surge arresters, protection, control, auxiliary systems and connections to incoming and outgoing circuits.

Important: The single-line diagrams show functional topology, not physical equipment layout. Circuit availability also depends on actual switch positions, protection zones, breaker-failure logic, remote-end tripping, transformer ratings and operating procedures. Disconnecting sequences, earthing switches and interlocks are intentionally simplified.

05 // HVAC versus HVDC

Most transmission networks are AC because transformers, protection and intermediate network connections are mature and widely deployed. HVDC is added where controlled point-to-point transfer or long cable distance offers a system benefit.

Alternating current

Voltage and current reverse direction periodically. Multiple AC generators remain synchronized within a synchronous area.

+V−V

Direct current

Polarity remains fixed. Power-electronic converters control transfer and connect the DC link to one or more AC systems.

FIXED POLARITYCONTROLLED POWER SETPOINT
QuestionHVACHVDC
How is voltage changed?Conventional power transformersPower-electronic converter stations plus AC transformers
How does power flow?Determined by network impedance and angle differencesConverter controls schedule the link transfer within limits
Long cable behaviourCharging current and reactive compensation become importantNo periodic AC charging current in normal DC operation
Connect asynchronous grids?Not directlyYes, through the DC link
Intermediate network connectionsRoutine in meshed gridsPossible but multi-terminal systems are more complex
Terminal cost and lossGenerally lower terminal complexitySignificant converter investment and converter losses
Fault interruptionMature AC breakers and protectionDC fault interruption and multi-terminal protection are more demanding

06 // Real transmission project examples

These short examples show why different transmission technologies are selected. The simulator calculations are generic and do not reproduce these projects.

Gotland HVDC — technology milestone

The original Gotland link entered service in 1954 and is widely recognised as the first commercial HVDC transmission system.

Original power20 MW
Original voltage100 kV
Route96 km
LessonSubmarine DC
Project history ↗

NorNed — long submarine interconnector

NorNed connects Norway and the Netherlands through a long HVDC submarine cable and supports controllable cross-border exchange.

Capacity700 MW
Length580 km
TypeHVDC cable
In service2008
HVDC project history ↗

North Sea Link — large interconnector

The Great Britain–Norway link illustrates modern high-capacity, long-distance submarine interconnection.

Capacity1.4 GW
Routeabout 720 km
TypeHVDC subsea
RoleGrid exchange
National Grid project page ↗

07 // Transmission engineering background

Open the topics below for the main physical and operational ideas represented by the simulator.

Lines, voltage and power

Transformers and substations

Related EngineerHub electrical tools

Continue from transmission principles into system operation, voltage drop, transformer ratios and circuit calculations.

Frequently asked questions