Skip to content

Drawing No. EH–CA–005 // Engineering Case Study

9 August 2019 Great Britain Power Outage

An interactive engineering reconstruction of the 9 August 2019 Great Britain (UK) power outage, showing how a correctly cleared lightning fault coincided with unexpected losses at Hornsea One, Little Barford and distribution-connected generation. The resulting 1,878 MW cumulative infeed loss drove frequency to 48.8 Hz, triggered Low Frequency Demand Disconnection and required coordinated frequency recovery and demand restoration.

Prepared by EngineerHub · Published and technically reviewed

Fault: 16:52:33.490Minimum frequency: 48.8 HzInfeed lost: 1,878 MWLFDD demand: 931 MW

01 // Interactive regional replay

Select a stage or run the event.

Great Britain Transmission System StatusPublished regional boundaries, event locations and a stage-dependent educational transmission backbone.
Regional geometry: published source · transmission topology and stage states: educational.
Great Britain regional power-system replay for the 9 August 2019 outage Geographic map of eleven Great Britain regions with an animated schematic transmission network and event locations at Hornsea One, Little Barford, Eaton Socon–Wymondley and Dinorwig. NORTH SEA ATLANTIC IRISH SEA ENGLISH CHANNEL EdinburghManchesterLondon HORNSEA ONE 737 MW LOSS LITTLE BARFORD 641 MW TOTAL EATON SOCON–WYMONDLEY 400 KV FAULT DINORWIG FAST RESPONSE !!
Current stageNormal system operation
Normal operation
Regional status
Normal
Stressed
Critical / LFDD
Demand disconnected
Restoring
Where
What changed
System effect
Response
System consequence
Measured scaleCumulative infeed loss
Stage 1 of 9Event progression

System indicators

FrequencyControlled
Deviation0.00 Hz
Minimum reached50.00 Hz
System stateSynchronous and energised

Rolling operator event console

2019 Great Britain power outage timeline

02 // System frequency

Source-based milestones with educational interpolation.

48.548.849.250.2LFDD OPERATING THRESHOLD
50.00 HzGreat Britain system frequency
ConditionControlled
Deviation0.00 Hz
Minimum shown50.00 Hz
System stateSynchronous and energised
Model boundary: source-based event milestones are connected by educational interpolation. The Great Britain system remained synchronised and energised throughout the disturbance.

03 // Cause-and-effect chain

The complete event in five engineering steps.

01 / FAULTLightning creates a short circuit that transmission protection clears in 74 ms.
02 / INFEED LOSSHornsea One, Little Barford and embedded generation disconnect unexpectedly.
03 / RESPONSE EXHAUSTEDResponse arrests the first decline, but another Little Barford trip removes remaining margin.
04 / LFDDFrequency reaches 48.8 Hz and 931 MW of demand is automatically disconnected.
05 / RECOVERYResponse, control-room actions and staged demand restoration return the system to normal.

04 // Event figures

Official milestones with explicitly labelled interpolation.

Cumulative infeed loss and LFDD demand

Cumulative infeed lossDemand disconnected
The final cumulative infeed loss was 1,878 MW; LFDD disconnected 931 MW of demand.
View infeed-loss and LFDD data
StageCumulative infeed loss (MW)Demand disconnected (MW)
1. Before 16:52:33 BST00
2. 16:52:33.490–.564 BST1500
3. 16:52:33–34 BST1,1310
4. 16:52:34–16:53:18 BST1,4810
5. 16:53:31 BST1,6910
6. 16:53:49.398 BST1,691931
7. 16:53:58 BST1,878931
8. 16:54:20–16:57:15 BST1,878931
9. 16:58–17:37 BST1,8780

Frequency transient

System frequency48.8 Hz LFDD trigger
Intermediate points are educational interpolation between official milestones.
View frequency data
StageFrequency (Hz)Condition
1. Before 16:52:33 BST50.00Near nominal
2. 16:52:33.490–.564 BST49.97Near nominal
3. 16:52:33–34 BST49.55Low
4. 16:52:34–16:53:18 BST49.20Low
5. 16:53:31 BST49.05Emergency
6. 16:53:49.398 BST48.80LFDD threshold
7. 16:53:58 BST48.95Emergency
8. 16:54:20–16:57:15 BST50.00Near nominal
9. 16:58–17:37 BST50.00Near nominal

Response and restoration actions

Frequency responseControl-room actionsRestoration progress ×12.4
The restoration series is scaled for display. Response and control actions are shown as reported milestones, not a dynamic dispatch trace.
View response and control-action data
StageFrequency response shown (MW)Control-room actions (MW)Demand restoration (%)
1. Before 16:52:33 BST000
2. 16:52:33.490–.564 BST000
3. 16:52:33–34 BST000
4. 16:52:34–16:53:18 BST90000
5. 16:53:31 BST1,00000
6. 16:53:49.398 BST1,00000
7. 16:53:58 BST1,00000
8. 16:54:20–16:57:15 BST1,0001,24015
9. 16:58–17:37 BST1,0001,240100

Broad regions by status

NormalStressedCriticalDemand disconnectedRestoring
Regional status is an educational geographic illustration, not an official DNO-by-DNO outage chronology.
View regional status data
StageNormalStressedCriticalOfflineRestoring
1. Before 16:52:33 BST50000
2. 16:52:33.490–.564 BST32000
3. 16:52:33–34 BST03200
4. 16:52:34–16:53:18 BST02300
5. 16:53:31 BST00500
6. 16:53:49.398 BST04010
7. 16:53:58 BST04100
8. 16:54:20–16:57:15 BST40001
9. 16:58–17:37 BST50000

05 // Event explanation

The transmission fault was cleared correctly. The widespread outage developed because several unexpected generation losses occurred almost simultaneously with the voltage disturbance and were followed by additional trips.

Why the first frequency decline stopped

Frequency response delivered at least 650 MW within about eleven seconds and 900 MW by 16:53:04. This arrested the first decline at 49.1 Hz and supported a recovery to 49.2 Hz.

Why frequency fell a second time

Little Barford GT1A then disconnected 210 MW while all available response was already being delivered. The system therefore had insufficient remaining headroom to absorb the new loss without emergency demand disconnection.

Why the map uses broad regions

Official reports provide national frequency, plant and DNO information, but not a continuous administrative-region animation. The map therefore uses five broad educational regions to show stress, LFDD and restoration without claiming an official geographic sequence.

Why transport disruption lasted longer

Electrical supplies were restored quickly, but some rail equipment and trains required manual restart or operational recovery. The page therefore distinguishes power-system restoration from dependent-infrastructure recovery.

07 // Event interpretation

What the event demonstrates about frequency security and dependent infrastructure.

The lightning strike was an initiating disturbanceThe fault itself was cleared correctly and did not represent a transmission-protection failure.
The secured loss was exceededThe near-simultaneous infeed losses exceeded the 1,000 MW secured loss level in force at the time.
Distributed generation changed the event scaleLoss-of-mains protection disconnected an estimated 500 MW of embedded generation and deepened the deficit.
LFDD prevented a more severe outcomeAutomatic demand disconnection rebalanced the system when response and reserve were insufficient.

08 // How the barriers performed

A concise view of prevention, protection and recovery barriers.

EffectiveTransmission fault protection

The 400 kV circuit fault was cleared within 74 ms and automatically reclosed.

Unexpected performanceGenerator fault ride-through and controls

Hornsea One and Little Barford experienced losses that were not expected for the cleared fault.

Insufficient for combined lossFrequency response and reserve

Response arrested the first decline but had no remaining margin when GT1A tripped.

Final defence successfulLFDD and staged restoration

931 MW of demand was disconnected automatically and restored after the system stabilised.

09 // Engineering background

Open each topic to review the principles illustrated by the event.

10 // Key engineering lessons

Four transferable lessons for modern low-carbon power systems.

Secure against credible combinations, not only one unitCommon-mode or coincident responses can exceed the nominal largest-infeed criterion.
Embedded generation must support system securityLoss-of-mains settings can amplify a transmission disturbance if large volumes disconnect together.
Emergency defence needs verified geographic performanceLFDD quantities, settings and customer consequences must be understood and tested across DNO areas.
Critical services need resilient restart arrangementsElectricity restoration alone does not guarantee rapid recovery of rail, communications and other dependent systems.

11 // Frequently asked questions

Short answers to common questions about the 9 August 2019 event.

12 // Related case studies

Compare this frequency event with other EngineerHub disturbance replays.

13 // Sources and model limitations

Primary reports and the boundaries of this educational reconstruction.