Facility demand
Average facility power is average IT load multiplied by PUE. Peak facility demand is entered separately so cooling and other coincident peaks can be represented.
Drawing No. EH–TH–054 // Data Center Engineering
Reviewed August 2026
Estimate how many nuclear reactor or SMR modules are required for a data center from average IT load, PUE, peak facility demand and resilience assumptions. Compare normal capacity, loss of one module, planned refuelling support and annual energy balance.
Reactor nameplate capacity, annual generation and continuity of supply are different questions. The model therefore checks them independently.
Average power used by servers and IT equipment.
Average total facility power divided by average IT power.
Include cooling, electrical losses and coincident peak margin.
Use net electrical output delivered at the plant boundary.
Used for annual energy only—not for the N+1 capacity check.
N+1 here means one reactor module unavailable.
Import capacity credited during a module outage.
Non-battery onsite generation available for the event.
Credited only for the short trip check.
Usable energy equals discharge power × duration.
| Capacity-only minimum | — |
|---|---|
| After one-module loss | — |
| Short-trip margin with all support | — |
| Refuelling margin without battery | — |
| Battery bridge check | — |
| Annual facility demand | — |
| Annual nuclear generation | — |
| Annual nuclear coverage | — |
Annual surplus is an arithmetic energy balance. It does not prove that the surplus can be exported or that every hourly load can be met.
transparent screening equations
Average facility power is average IT load multiplied by PUE. Peak facility demand is entered separately so cooling and other coincident peaks can be represented.
The capacity-only count is peak load divided by net output per module, rounded up. For N+1, the design must also pass the one-module-unavailable refuelling check.
Annual nuclear generation uses the entered capacity factor. Planned outage inputs describe scheduling frequency but are not deducted again because their effect should already be reflected in capacity factor.
read before using the result
Capacity factor measures annual energy production relative to continuous full-power operation. Two projects with the same capacity factor can have different forced-outage rates, maintenance schedules and common-mode risks. This calculator therefore does not use capacity factor in the instantaneous N+1 capacity equation.
The N+1 case removes one complete reactor module. The short-trip check credits remaining nuclear capacity, firm grid import, firm backup generation and battery discharge power. The planned-refuelling check excludes the battery because a multi-week outage normally exceeds practical battery energy duration.
It does not model simultaneous grid loss, common-cause events, switchgear faults, transformer failures, bus topology, black start, protection or the reliability of the credited support sources.
PUE is normally an annual or operating-period ratio. Multiplying average IT load by average PUE gives average facility demand, not necessarily the coincident peak. Peak cooling, UPS losses, charging, redundancy and ambient conditions can produce a different maximum. The calculator therefore requires an explicit peak facility value and warns when it is lower than the calculated average.
A positive annual balance means calculated nuclear generation exceeds calculated facility consumption over a year. It does not establish hourly matching, export rights, transmission capacity, minimum stable reactor power, load-following capability, curtailment, market value or the availability of another consumer for surplus electricity.
common sizing questions
Divide peak facility demand by net reactor-module output and round up for the capacity-only minimum. If one module must be allowed to trip or refuel without interrupting the data center, test the remaining modules together with only the support sources that can actually remain available.
No. Capacity factor is an annual energy measure. It does not replace availability, reliability, common-cause failure, electrical distribution or grid studies.
A battery can bridge a short event when both its MW and MWh ratings are sufficient. This model does not count battery capacity as multi-week refuelling support. Grid import or firm backup generation is required if the remaining reactor modules cannot serve the selected load.
Not necessarily. One module may substantially exceed the campus load, while a nuclear-only N+1 criterion can require a second module. Unless surplus electricity has another use, a smaller module, firm grid connection or shared generation arrangement may fit better.
official sources and model context
The module-size buttons are generic comparison presets, not statements that any particular design is licensed, commercially available or suitable for a data-center project.
Describe the issue and include the input values that produced it.